LOCATION & OWNERSHIP

Målselv municipality
Private property

SITE DETAIL

Flat, levelled site some with vegetation, mainly birch. Clearing of vegetation is progress. 

ZONING PLAN

Zoning and construction permit is ongoing with consideration for data centers. An exceptional permit can be applied for site preparation prior to construction. 

 

Sites are located in North of Andslimoen businesses area with a total of 18.7 Ha and a 30Ha extension plot West of E6.  

POWER

100% renewable energy from hydropower. The current power supply is 7MW at 22kv by Troms Kraft AS. The site can deliver up to 132kv, 200MW with N-1 redundancy in 3-5 year from order/investment decision.

CONNECTIVITY

Redundant dark fibre can be delivered within  2 months.

CLIMATE

Fresh air cooling available all year around 
Average low: -0.7°C
Average high: 5.8°C

SITE ACCESS

7 km to Bardufoss Airport

131 km to Tromsø Airport 
Tromsø city is 2
hour drive away ( 161 000 inhabitants) via E8 and E6
 

By plane
Tromsø to Oslo and Stockholm - 2hr
Tromsø to London Gatwick - 3hr (Nov-May)

ENVIRONMENT

 No apparent geohazard or earthquake recorded. 

Målselv Municipality

Andslimoen

Lively industry area with large area for hyper-scale data center expansion 