LOCATION & OWNERSHIP
Målselv municipality
Private property
SITE DETAIL
Flat, levelled site some with vegetation, mainly birch. Clearing of vegetation is progress.
ZONING PLAN
Zoning and construction permit is ongoing with consideration for data centers. An exceptional permit can be applied for site preparation prior to construction.
Sites are located in North of Andslimoen businesses area with a total of 18.7 Ha and a 30Ha extension plot West of E6.
POWER
100% renewable energy from hydropower. The current power supply is 7MW at 22kv by Troms Kraft AS. The site can deliver up to 132kv, 200MW with N-1 redundancy in 3-5 year from order/investment decision.
CONNECTIVITY
Redundant dark fibre can be delivered within 2 months.
CLIMATE
Fresh air cooling available all year around
Average low: -0.7°C
Average high: 5.8°C
SITE ACCESS
7 km to Bardufoss Airport
131 km to Tromsø Airport
Tromsø city is 2 hour drive away ( 161 000 inhabitants) via E8 and E6
By plane
Tromsø to Oslo and Stockholm - 2hr
Tromsø to London Gatwick - 3hr (Nov-May)
ENVIRONMENT
No apparent geohazard or earthquake recorded.
Målselv Municipality
Andslimoen
Lively industry area with large area for hyper-scale data center expansion
![]() Exsisting industry areaphotographed by Tromsø Dronefoto | ![]() Robust transportphotographed by Tromsø Dronefoto | ![]() Exciting opportunities in Andslimoenphotographed by Tromsø Dronefoto |
---|---|---|
![]() Minutes away from Bardufoss airportphotographed by Tromsø Dronefoto | ![]() Nearby substationphotographed by Tromsø Dronefoto | ![]() Iconic Målselv river nearbyphotographed by Tromsø Dronefoto |
![]() Målselv Municipality |