top of page

LOCATION & OWNERSHIP

Harstad municipality
Private property of Eiendomsselskapet BRT AS

SITE DETAIL

Flat, levelled site with high-quality granite on site

ZONING PLAN

Zoning and construction permit is ongoing with consideration for hyperscale datacenters. 

 

Sites are has a total area of 62.5 Ha.

Building phase 1: 26 Ha

Building phase 2: 16 Ha

Building phase 3: 20.5 Ha

 

with the opportunity to an expansion. 

POWER

100% renewable energy from hydropower. The site can deliver up to 132kv, 250MW with N-1. Power is delivered by HålogalandsKraft AS and can deliver connection within 48 months from order/investment decision.

CONNECTIVITY

Redundant dark fiber delivered by Bredbåndsfylket Troms, Broadnet, Telenor

 

Potential for up to 4 independent routes out of the location

CLIMATE

12months of fresh air cooling
Average low: -7.2°C
Average high: 5.2°C

SITE ACCESS (driving time)

4 km to Harstad 

75 km to Narvik (1hr10min)

45 km to Evenes Airport (40min)

257 km to Tromsø (3hr40min)

260 km to Kiruna, Sweden (3hr30min)


By plane
Evenes Airport to Oslo - 1.5 hr
Tromsø Airport to Oslo - 2 hr

ENVIRONMENT

Location is 200-300 m from water supply. Up to 50 l/s of filtered river water available for cooling. No apparent cultural heritage or archaeological sites are recorded.

Harstad Municipality

Langmoan

Large industry area along the coast. Stone-throw away from Harstad centre with the local industry of oil and gas and good transport connection. 

Bjørn Rasch-Tellefsen

Project leader - BRT

brt@brteiendom.no
tlf: +47 9132 5195

bottom of page